Owner: Centralia School District

General Contractor: Pacific Mobile Structure Inc

Engineer: SCJ Alliance

Contract Value: $349,000.00

In the spring of 2020, Odyssey subcontracted to Pacific Mobile Structures Inc to provide a complete site work package including but not limited to; building pad preparation, sewer line installation, water line installation, stormwater infiltration piping, electrical conduit bore under roadway, paving, fencing, site concrete, landscaping and existing structure demolition for the install of (4) brand new mobile classroom structures at the Centralia Middle School.